Project Management Network Diagrams Prof. Mauro Mancini

Similar documents
Research on the Milestones Takt Time of the General-Assembly Shipbuilding

Effective Machine Layout to Minimize the CM for T-shirt & Polo-shirt

Assessment Schedule 2016 Economics: Demonstrate understanding of producer choices using supply (90985)

Balanced Assessment Elementary Grades Package 1 Dale Seymour Publications Correlated To I Get It! Math Grades 3-5 Modern Curriculum Press

Balanced Assessment Elementary Grades Package 1 Dale Seymour Publications Correlated To I Get It! Math Grades 3-5 Modern Curriculum Press

Clothes Recommend Themselves: A New Approach to a Fashion Coordinate Support System

Regulatory Genomics Lab

ALASKA GROSS STATE PRODUCT

Using ONYX Separation Control Tool. Contents: What is Separation Control? Using ONYX Separation Control Tool. Separation Control Tips and Tricks

Improvement in Wear Characteristics of Electric Hair Clipper Blade Using High Hardness Material

GALLERY SHOES. International Tradeshow for Shoes & Accessories 27 th 29 th August 2017 in Düsseldorf

C. J. Schwarz Department of Statistics and Actuarial Science, Simon Fraser University December 27, 2013.

Higher National Unit Specification. General information for centres. Fashion: Commercial Design. Unit code: F18W 34

Comparison of FlexPLI Performance in Vehicle Tests with Prototype and Series Production Legforms

Image courtesy of istockphoto.com/atomic Sparkle

Servant Leadership and other Lessons Learned from the Montreal Olympic Stadium. Tina Cerulli, PMP Presentation to PMI Champlain Valley

SWBAT: Describe and Apply the Rule and the standard Normal Distribution. Lesson 2-2 The Rule Although there are many Normal

For- Credit Courses and Certificate Programs in Apparel Merchandising & Management for Industry Professionals

Session 10. Sourcing and Supplier Management Practices

INTEGRATION OF PREDETERMINED MOTION TIME SYSTEMS INTO SIMULATION MODELING OF MANUAL CONSTRUCTION OPERATIONS

Freedom Line RMN with INNOVATOR Doors or INNOVATOR III Doors Technical Data Sheet P/N _D NSF Certified December 2012

How to Simplify Your Frac Site. Presented by Firstname Surname, Job Title

Personal Effectiveness Competencies. Time Management

The Business of Textile and Fashion

AN INDEPENDENT ASSESSMENT OF INK AGE DETERMINATION BY A PRIVATE EXAMINER Erich J. Speckin

Higg.org Platform Update What to Expect: Timeline and Next Steps

Quality Assurance Where does the Future Lead US. John D Angelo D Angelo Consulting, LLC

OPTIMIZATION OF MILITARY GARMENT FIT

Sampling Process in garment industry

Fashion Pricing and Technology. Back to Table of Contents

INDUSTRY AND TECHNOLOGY Institutional (ILO), Program (PLO), and Course (SLO) Alignment

MNPE In Collaboration with. Karnataka State Open University. Manasagangotri, Mysore-6. Syllabus Certificate in Fashion Designing

What is econometrics? INTRODUCTION. Scope of Econometrics. Components of Econometrics

Case 2 VSM case: assembly of printed circuit board.

Case Study : An efficient product re-formulation using The Unscrambler

Framingham State University. Program Assessment Plan for (Fashion Design and Retailing)

Clinical studies with patients have been carried out on this subject of graft survival and out of body time. They are:

Chapman Ranch Lint Cleaner Brush Evaluation Summary of Fiber Quality Data "Dirty" Module 28 September 2005 Ginning Date

little treasures 2019

This unit is an optional unit included in the framework of the SQA Advanced Certificate /Diploma in Retail Management.

topical + tropical sensorial experience

Tips for proposers. Cécile Huet, PhD Deputy Head of Unit A1 Robotics & AI European Commission. Robotics Brokerage event 5 Dec Cécile Huet 1

ISSN: [Hanan* et al., 7(7): July, 2018] Impact Factor: 5.164

BUSINESS STRATEGY AND POLICY - MGMT3031

How to check the printing process

BONO submission on the Consultation in preparation of a Commission report on the implementation and effect of the Resale Right Directive (2001/84/EC)

UNIT TITLE: PREPARE AND DISPLAY PETIT FOURS NOMINAL HOURS: 35

Unit 329 Level 3 vrq Beauty Therapy. Beauty Therapy L3 VRQ_Unit 329_Proof 5.indd 258. Image courtesy of istockphoto.com/tatianamironenko

Predetermined Motion Time Systems (PMTS) CHAPTER 10

Provide colour correction services

29 January Cullinan Grade versus Value Analysis. Background

Who is Bovie Animal Health?

A Comparison of Two Methods of Determining Thermal Properties of Footwear

Hair colour correction services

SALES (EURO 7.94 BLN) AND TRADE SURPLUS (EURO 2.3 BLN) FOR

Case Study Example: Footloose

Fashion Merchandising and Design. Fashion Merchandising and Design 10

Cluster 6.3: Number and Operations

TEXTILES, MERCHANDISING AND FASHION DESIGN (TMFD)

Candidate. Number Other Names

APPENDIX I. ANALYSIS OF THE CURRENT STATE

FASHION DESIGN AND MERCHANDISING

Global Fast Fashion Market with Focus on The United States: Size, Trends & Forecast ( ) June 2016

CAPRI HOLDINGS LIMITED

OpenSesame EyeLink tutorial

Sephora Body Care Centers Marketing Plan 2011

Hyalurosmooth. by Beauty Creations. Natural fine line and wrinkle filler

US Denim Jeans Market Report

Fairfield Public Schools Family Consumer Sciences Curriculum Fashion Merchandising and Design 10

Fairfield Public Schools Family Consumer Sciences Curriculum Fashion and Design 30/40

AESTHETIC PRECISION THE SAFEST AND MOST PRECISE LASER TREATMENT SOLUTION AVAILABLE FOR PIGMENTED LESIONS AND MULTI-COLOR TATTOO REMOVAL

RESEARCH SUSTAINABILITY - H&M MADELEIN DE GRAAF & ASTRID VAN LOON

CHAPTERS RESEARCH DESIGN

Hairdressing and Electrolysis Program (operc / operc e) Read Below for Complete Course Description

Enhance nails using electric files Unit 320 1

China Home Textile Industry Overview,

Explore technological developments within the hair, beauty and associated areas Unit 332 1

China Home Textile Industry Report, Apr. 2013

EL DORADO UNION HIGH SCHOOL DISTRICT EDUCATIONAL SERVICES Course of Study Information Page. History English

Philadelphia University Faculty of Pharmacy Department of Pharmaceutical Sciences First Semester, 2017/2018. Course Syllabus. Course code:

THE VENUS VIVA EXPERIENCE

SM ART FAC IA L CLEANSING & MASSAGING BRUSH

SNOW MODELLING IN AUSTRIA

China Cosmetics Market Report, Feb. 2012

Impact of Marker Width to Optimize Fabric Cost of Garments Md. Rafiqul Islam Manik 1, Ishrat Jahan 2

Using Graphics in the Math Classroom GRADE DRAFT 1

Services for Personal Protective Equipment Testing and certification

Department of Industrial Engieering. Chapter : Predetermined Time Systems (PTS)

Testing Services for the Evaluation of. Fabric Systems, Clothing Systems, Sleeping Bag Systems, Bedding Systems, and Personal Cooling Systems (PCS)

STUDY TITLE: Effects of LifeWave Y-age Anti-Aging patches on varied skin types

S H A R E H O L D E R S M E E T I N G J U N E

Overcoming OBI in RFoG Networks. Michael McWilliams ANGA Cologne, Germany June 9, 2016

Effect of Hair Style on Human Physiological Responses in a Hot Environment

MEDICAL OIL-FREE COMPRESSORS

SERIATION: Ordering Archaeological Evidence by Stylistic Differences

To Study the Effect of different income levels on buying behaviour of Hair Oil. Ragde Jonophar

This unit is suitable for those who have no previous qualifications or experience.

ADVANTAGES: Stop waste mix as much as you need, by a minimum of 1/2 Kg. Lower purchase cost, resulting from the difference in cost with

DISCLAIMER: This document is for informational use only. All decisions as to what protective clothing must be worn should be determined by your

Establishment of a Universal Size Conversion Chart for Men s Sportswear

Transcription:

Project Management Network Diagrams Prof. Mauro Mancini e-mail: Mauro.Mancini@polimi.it tel.: +39-02-23994057 POLITECNICO DI MILANO Department of Management, Economics and Industrial Engineering Mauro Mancini Planning s Instruments MILESTONES GANTT CHARTS S CURVES NETWORK DIAGRAMS SPACE-TIME DIAGRAMS DATA TABLES Mauro Mancini 2

Precedence Chart Mauro Mancini 3 Gantt Chart Schedule Activities Mauro Mancini 4

Resources Scheduling Resources Schedule Mauro Mancini 5 Pattern Mauro Mancini 6

Gantt Chart Gantt Chart shows when the project and each activity start and end against a horizontal timescale (bar chart) Steps: Activities have to be sequenced Activity s duration has to be estimated Gantt Chart can be drafted and refined Mauro Mancini 7 Gantt Chart Advantages Easy elaboration Direct graphics Possibility to easy evaluate the resources requested by the whole activities Mauro Mancini 8

Gantt Chart Limitations Suitable for projects composed by few activities It (usually) doesn t indicate the logical relationships between activities Mauro Mancini 9 Network Diagrams Unlike the Gantt chart, the network diagrams show a systemic project representation. In this way they allow to define the project like the whole linked activities oriented to an unique objective. Mauro Mancini 10

Network Diagrams Project operative model What if analysis Mauro Mancini 11 Network Diagrams They allow to link together activities (or work package) making possible: the construction of logical model the construction of schedule model to verify the project s feasibility to correctly allocate the activities resources Mauro Mancini 12

Network Diagrams They allow to link together activities (or work package) making possible: to give a inter-functional visibility to individualize the critical activities to simulate the impact from time and cost variations or, more generally, from eventual problems or corrective actions Mauro Mancini 13 Graphs A graph is a set of nodes linked by arrows, their sequence define a path. If the arrows have a sense, the graph is called oriented. Mauro Mancini 14

Graphs types Without circuits With circuits With certain paths With uncertain paths With AND nodes With OR nodes With probabilistic node Mauro Mancini 15 Graphs types Activity on arrow Activity A Activity B Start A Case End A Case / Start B Case End B Case Activity on node Activity A Activity B Activity A Activity B Connection Mauro Mancini 16

Example 1 Activity on arrow Mauro Mancini 17 AOA Networks FINISH TO START links Dummy activities requested The dummy activities are not characterized by duration or resources use. They only establish precedence constraints between the activities Mauro Mancini 18

AON Networks Link types Finish to Start Start to Start Finish to Finish Start to Finish Each activity can have more than one input and output link Between two activities is possible to have two different types of link Dummy events (milestones) can be used Mauro Mancini 19 Example 2 Activity on node Mauro Mancini 20

Types of Graphs Without Circuits Certain Durations Uncertain Durations Link types FS FS-FF-SS-SF FS Methods CPM PDM Pert Output (Durations) Deterministic Probabilistic Uncertain Paths Uncertain Durations Every Links Simulations Mauro Mancini 21 Links types A FS B FINISH - START A SS B START - START A FF B FINISH - FINISH A SF B START - FINISH (not much used) Mauro Mancini 22

Links types B 1 B 2 A 1 A 2 FF1 A B SS1 Mauro Mancini 23 Lead Time Tree P1.1 P1.2 M1.2 P2.1 P2.2 A2 A1 LT 2 LT 1 A Production Lead Time Time PLT Delivery Lead Time? Mauro Mancini 24

Terminology and definitions EOTi Earliest Occurrence Time (event i) LOTi Latest Occurrence Time (event i) ESTik Earliest Starting Time (activity ik) EFTik Earliest Finishing Time (activity ik) LSTik Latest Starting Time (activity ik) LFTik Latest Finishing Time (activity ik) tik Time (activity ik) Mauro Mancini 25 Terminology and definitions i = 0 i = N indicates the start project node indicates the end project node A i = set of nodes x for which the xi arc exists and converges on I B i = set of nodes y for which the iy arc exists and comes from i Mauro Mancini 26

Activity Duration Planning Process Resource Needed AVAILABLE RESOURCES WBS Standard Productivity Corrective factors QUANTITY PRODUCTIVITY NEEDED RESOURCES ESTIMATED ACTIVITY DURATION ESTIMATED ACTIVITY COST Accounting Standard Cost UNIT COST Knowledge Historical DB Experience Mauro Mancini 27 Earliest and Latest Dates Calculation The algorithm to calculate the network activities' dates is composed by two phases: Forward pass (earliest dates calculation) Backward pass (latest dates calculation) Mauro Mancini 28

Earliest and Latest Dates Calculation Dates are scheduled in the two versions: earliest, anticipating the activities that are not in the critical paths to the earliest dates latest, postponing anticipating the activities that are not in the critical paths to the latest dates CONVENTION: activity start = unit of time start activity end = unit of time end FT = ST + d -1 ST = FT d -1 d = FT ST +1 Mauro Mancini 29 Forward Pass Beginning from the start project node (node 0) end going toward the end project node all the earliest start and finish dates for each event/activity are computed EOT 0 = 0 EST ik = EOT i + 1 EFT ik = EST ik + t ik - 1 EOT k = max j Ak (EFT jk ) Mauro Mancini 30

Forward Pass 1 10 A 10 11 15 B 5 16 25 D 10 11 20 C 10 26 30 E 5 ES Att t EF EF = ES + duration -1 Mauro Mancini 31 Backwad Pass It is necessary to consider the end project event (node N) and to set its maximal date (LOT N ) equal to the lowest date EOT N computed in the previous pass LOT N = EOT N LFT ik = LOT k LST ik = LFT ik - t ik + 1 EOT i = min l Bi (LST il ) - 1 Mauro Mancini 32

Backward Pass 1 10 A 10 1 10 11 15 16 25 B 5 D 10 11 15 16 25 11 20 26 30 C 10 E 5 16 25 26 30 LS = LF duration + 1 Mauro Mancini 33 Backwad Pass From the resulting dates is possible to know: The internal interrelationship logic The activities durations It is possible to assign to LOT N values (different from EOT N ) imposed by external constraints to the network logic (contractual expiration date, ) It is established: if degrees of freedom exist where to share eventual negative TF Mauro Mancini 34

Exercise (1/3) From the data in the table draw: the precedence diagram the allocated resources profile the Gantt chart Assuming that there are infinite resources available and not temporal constraints WP Precedence Duration res. per day A / 8 4 B / 6 4 C / 7 5 D A 5 4 E A,B 6 10 F E,C 9 9 G D,E 4 2 H G,F 2 2 Mauro Mancini 35 Exercise (2/3) 1 8 9 13 A D 15 18 1 8 15 19 G 1 6 9 14 24 25 20 23 B E H 15 23 3 8 9 14 24 25 F 1 7 C 15 23 8 14 Mauro Mancini 36

Exercise (3/3) 14 13 12 11 10 9 8 7 6 5 4 3 2 1 A B C D E F G H D B G C E F A H 2 4 6 8 10 12 14 16 18 20 22 24 26 2 4 6 8 10 12 14 16 18 20 22 24 26 Mauro Mancini 37 Float Calculation According to the comparison among the earliest and latest dates, through the floats examination it is possible to individualize the project critical activities: The following types of float are defined: Total float Free float Independent float Mauro Mancini 38

Total Float Total float is the maximum interval available to postpone or extend the execution for a single activity, without change the project deadline Mauro Mancini 39 Total Float It is calculated using the following relationships: Sti k = LFT ik - EFT ik = LFT ik - (EST ik + t ik - 1) = = (LFT ik - t ik + 1) - EST ik = LST ik - EST ik = = (LOT k - t ik + 1) - EOT i - 1 = LOT k - EOT i - t ik It represents the maximum interval available to reallocate the activities Mauro Mancini 40

Float Calculation 1 10 A 10 1 0 10 11 15 B 5 11 0 15 16 25 D 10 16 0 25 ES EF A 10 LS float LF 11 20 C 10 16 5 25 26 30 E 5 26 0 30 Mauro Mancini 41 Not Critical Activities EST duration EFT float float LST duration LFT Mauro Mancini 42

Critical Activities EST EFT LST duration LFT float = 0 Mauro Mancini 43 Free Float (FF) Float available for the activity without need to postpone the earliest start date for the successive node (k) Hypothesis: the starting node (i) is earliest realized Mauro Mancini 44

Free Float (FF) The following relationships are assumed: Sl ik = EOT k - EFT ik = EOT k - (EST ik + t ik -1) = = EOT k - EOT i - t ik It always results: SL ik ST ik Mauro Mancini 45 Independent Float Acceptable delay for an activity with the hypothesis that the starting date was the latest start date and the finish activities (successive activity starting) must be realized at the earliest start date. The independent float does not influence the previous and successive activities Mauro Mancini 46

Independent Float It is calculated with the following relationship: SI ik = EOT k - LOT i - t ik It always results SI ik SL ik ST ik Mauro Mancini 47 Float Graphic Representation EOT i LOT i EOT k LOT K STi k = LOT k - EOT i - t ik SL ik = EOT k - EOT i - t ik SI ik = EOT k - LOT i - t ik Mauro Mancini 48

Temporal Constraints on Nodes NET not earlier than (forward pass) NLT not later than (backward pass) ON (forward e backward pass) Mauro Mancini 49 Critical Path It is the activities chain characterized by the maximal comprehensive duration or by the minimal float A delay for any activity belonging to the Critical Path implies a delay for the whole project. In order to reduce the whole project duration (10-20%) is necessary to operate on the critical path s activities. Mauro Mancini 50

If EOT N = LOT N Critical Path TF=0 If there are temporal constraints on the nodes the critical path could not be the path with the maximal duration. Mauro Mancini 51 Network Diagrams' Limits In order to achieve reliable analysis it is necessary to consider a great amount of activities to use sophisticated logical links It necessary to consider a great amount of data about: activities' attributes How the attributes change changing the activities Mauro Mancini 52

Network Diagrams' Limits The problems about data s updating are increased by the method analyticity After each updating it is necessary to critically verify the results, analyzing the development for the logical project concatenations The method does not allow to carry out previsione a finire on the base of advancing data Mauro Mancini 53 CPM tips If you need to accelerate the schedule, do it by fast-tracking and crashing. Watch out! Accelerating the schedule may increase the number of critical activities. (from 10 percent to 40-50 percent of activities will result critical). Sprinkle major milestones over your CPM chart. It helps you see woods (milestones) and trees (activities). Mauro Mancini 54

CPM tips Color-code activities performed by various resource providers in order to identify their interfaces and provide their coordination. Develop template CPM charts. Then, use them consistently to develop the schedule for new projects. Mauro Mancini 55 Cost Critical Path Method (CPM) It considers the time/costs trade-off normal duration/cost crashed duration/cost It tries to reduce the project duration to the least necessary expense find the critical path compact the critical path activities beginning from the least expensive repeat the process until dc/dt < dbenefits/dt Estimated Duration 1 2 3 4 HR Allocated Mauro Mancini

Cost Critical Path Method (CPM): example ACTIVITY PRED. NORMAL TIME NORMAL COST CRASHED TIME CRASHED COST dc/dt A - 3 30 2 40 10 B A 2 30 1 65 35 C A 2 60 / / / D A 3 60 2 75 15 E B 3 30 2 45 15 F C 1 30 / / / G D 1 60 / / / suppose that the customer would give a prize of 40 for every unitary reduction of delivery times Mauro Mancini Cost Critical Path Method (CPM): example Activity G Activity D Activity F Activity C Activity E Activity B Activity A 0 1 2 3 4 5 6 7 8 9 10 Activity Pred. Early Start Early Finish Late Start Late Finish dc/dt A - 0 3 0 3 10 B A 3 5 3 5 35 C A 3 5 5 7 / D A 3 6 4 7 15 E B 5 8 5 8 15 F C 5 6 7 8 / Mauro GMancini D 6 7 7 8 / Project duration= 8 Project Cost= 210 Critical Activities A, B, E A is the candidate for crashing

Cost Critical Path Method (CPM): example Activity A Activity C Activity B Activity D Activity F Activity G Activity E 0 1 2 3 4 5 6 7 8 9 10 Activity Pred. Early Start Early Finish Late Start Late Finish dc/dt A - 0 3 0 3 na B A 3 5 3 5 35 C A 3 5 5 7 / D A 3 6 4 7 15 E B 5 8 5 8 15 F C 5 6 7 8 / Mauro GMancini D 6 7 7 8 / Project Duration = 7 Project Cost = 220 Marginal Cost = 10 Marginal Revenue= 40 Profit = 30 Critical Activities A, B, E E is the candidate for crashing Cost Critical Path Method (CPM): example Activity A Activity G Activity D Activity F Activity C Activity E Activity B 0 1 2 3 4 5 6 7 8 9 10 Activity Pred. Early Start Early Finish Late Start Late Finish dc/dt A - 0 3 0 3 na B A 3 5 3 5 35 C A 3 5 5 7 / D A 3 6 4 7 15 E B 5 8 5 8 na F C 5 6 7 8 / Mauro GMancini D 6 7 7 8 / Project Duration = 6 Project Cost = 235 Marginal Cost = 15 Marginal Revenue = 40 Profit = 25 Critical activities: A, B, E and A, D, G D e B are both candidate for crashing

Cost Critical Path Method (CPM): example Activity A Activity B Activity D Activity C Activity E Activity G Activity F 0 1 2 3 4 5 6 7 8 9 10 Activity Pred. Early Start Early Finish Late Start Late Finish dc/dt A - 0 3 0 3 na B A 3 5 3 5 na C A 3 5 5 7 / D A 3 6 4 7 na E B 5 8 5 8 na F C 5 6 7 8 / Mauro GMancini D 6 7 7 8 / Project Duration = 5 Project Cost = 285 Marginal Cost = 50 Marginal Reveneu = 40 Profit = -10 Critical Activities: A, B, E; A, D, G and A, C, F The profit is negative, we refuse to crash B and D Link Between Activities Representation Methods a) SS ij b) FF ij c) FS ij d) SF ij Mauro Mancini 62

SS ij FF ij FS ij SF ij Link Between Activities Representation Methods Start to Start Minimal number of units of time that must be past from the previous activity s start to allow the successive activity to start Finish to Finish Minimal number of units of time required to complete the successive activity after the previous activity s completion. Finish to Start Minimal number of units of time that must be past from the previous activity s completion to allow the successive activity to start Start to Finish Minimal number of units of time that must be past from the previous activity s start to the successive activity s completion Mauro Mancini 63 Precedence Diagrams D A = 5 FF15 SS2 D B = 10 ES = 3 EF = 20 [11] Mauro Mancini 64

Precedence Diagrams - Forward Pass It is necessary to consider the constraint relative to the considered activity predecessors (Start e Finish) FS ij ES j = EF i + lag + 1 SS ij FF ij ES j = ES i + lag EF j = EF i + lag SF ij EF j = ES i + lag - 1 In case of many predecessors it is necessary to consider the maximal date Mauro Mancini 65 Precedence Diagrams - Forward Pass - Example A 171 B 158 C 180 D 187 E 177 F 182 20 190 30 187 20 199 10 196 40 216 25 206 FS = 0 FS = 0 SS = 10 SS = 5 FF = 10 FF = 18 Activity I 192 ES Duration 30 226 EF Mauro Mancini 66

Precedence Diagrams - Forward Pass - Example ES (I/A) = 190 + 0 + 1 = 191 ES (I/B) = 187 + 0 + 1 = 188 ES (I/C) = 180 + 10 = 190 ES (I/D) = 187 + 5 = 192 EF (I) = 192 + 30-1 = 221 EF (I/E) = 216 + 10 = 226 EF (I/F) = 206 + 18 = 224 Mauro Mancini 67 Precedence Diagrams - Forward Pass - Example In general: EF = ES + d -1 In presence of external predecessors for its finish (FF and SF), it is possible having incongruities. Activities s Splitting Mauro Mancini 68

Precedence Diagrams - Forward Pass - Splitting Example A 109 20 128 FF = 15 B 95 40 143 (134) A 109 20 128 B2 129 15 143 B1 95 25 119 (9) Mauro Mancini 69 Precedence Diagrams - Backward Pass It is necessary to consider the constraint relative to the considered activity successors (Start e Finish) FS ij LF j = LS i - lag - 1 SS ij FF ij LS j = LS i - lag LF j = LF i - lag SF ij LS j = LF i - lag - 1 In case of many predecessors it is necessary to consider the minimal date Mauro Mancini 70

Precedence Diagrams - Backward Pass - Example FS = 0 A 133 20 152 Activity Duration I 30 95 129 LS LF FS = 5 FF = 10 SS = 10 B 143 30 172 C 40 100 139 E 105 20 124 SS = 15 F 118 30 147 Mauro Mancini 71 Precedence Diagrams - Backward Pass - Example LF (I/A) = 133-0 - 1 = 132 LF (I/B) = 143-5 - 1 = 137 LF (I/C) = 139-10 = 129 LS (I) = 129-30 +1 = 100 LS (I/E) = 105-10 = 95 LS (I/F) = 118-15 = 103 Mauro Mancini 72

Precedence Diagrams - Backward Pass - Example In general: LS = LF - d -1 In presence of external predecessors for its start (FS and SS), it is possible having incongruities. Activities s Splitting Mauro Mancini 73 Precedence Diagrams - Backward Pass - Splitting Example A 203 (208) 30 237 SS = 10 B 213 30 242 A1 203 10 212 (5) A2 218 B 213 20 237 30 242 Mauro Mancini 74